Planned Performance
Indicators |
Actual Progress during the Reporting Period |
|
1 |
Awareness programme for the Government
agencies, NWSDB, NGOs and CBOs |
An awareness meeting was conducted for
government officials, stakeholders and national and
international agencies working in the area. |
|
2 |
Meeting with local masons to share
their experiences |
A meeting was conducted with the
trained masons and the masons who were trained
through “training on the job” |
|
3 |
Assessment of sites of the right
holders |
Householders at initial targeted
location at Peeriyanelavanai rejected the rain water
harvesting system. Therefore in cooperation with the
NWSDB, the Municipal Council and the DPDHS sites were
identified in Pandiruppu, Alamkulam and Savordayapura |
|
4 |
Training of local masons |
4 masons got trained through a
“training on the job” program |
|
5 |
Meeting with masons to follow up on the
construction process |
All together 3 meetings with the masons
were held to discuss problems, constraints and
challenges during the implementation. As a result the
implementation process was improved and the
construction became more efficient. |
|
6 |
Awareness meeting with identified
families |
Awareness programs for right holders
and public were conducted at Pandiruppu, Alamkulam and
Savordayapura |
|
7 |
Awareness creation among the right
holders and public on the benefits of rain water
harvesting |
During the implementation the interest
for RWH in the area increased and right holders and
public got to know the benefits of RWH systems |
|
8 |
Construction of rain water tanks in the
target areas |
By the end of April
2007, 100 x 5 m3 Rain Water Harvesting
Tanks have been constructed in Ampara district.
|
-
Kalmunai division 33 RWH tanks |
|
-
Addalchenai
division 37 RWH systems |
|
-
Pottuvil division 30 RWH systems |
|
|
9 |
Awareness creation for right holders on
care and maintenance |
Conducted at Periyaneelavanai,
Pandiruppu, Alamkulam and Savordayapura |
|
10 |
Hygiene promotion activities on
personal hygiene to reduce the incidence of water
related diseases for the right holder families |
3 main Hygiene Promotion lesson were
held in the project area. Furthermore hygiene
promotion activities were conducted in connection with
the care and maintenance meetings, mentioned above. |
|
11 |
Assessment of the usage of 1-30
constructed tanks |
An evaluation survey of the usage of
the individual RWH systems was done. 10 tanks in each
of the 3 areas were assessed. |
|
12 |
Final assessment on finishing of the
RWH systems |
Was completed May 2007. |