A Pilot Project on Dual Purpose Rain Water Harvesting Systems in North and East of Sri Lanka

 
     
     
 
Project Area : All eight districts in North & East of Sri Lanka (Ampara, Batticaloa, Trincomalee, Vavuniya, Kilinochchi, Mullativu, Mannar and Jaffna)
     
Duration : 15th August 2003 to 30th November 2005
     
Funded by : Aus AID (Australian Agency for International Development)
     
   
     
     
Objective : To improve the life standard of the people living in North and Eastern province of Sri Lanka through better access to domestic water supply.
 
     
     
  Outputs of the Project (at the completion - November 2005)  
     
 
1 Developed linkages with government, non government and other volunteer organisations in the project area. 55 local organizations, CBOs were linked with the LRWHF.
   
2 8 awareness creation workshops on the importance of RWH was conducted and 342 persons participated. The participants included  government and non government officers and the community.
   
3 A symposium and exhibition on RWH technology was held in Jaffna. An awareness exhibition was held at Trincomalee in September 2004 focusing school children on RWH technology and other appropriate technologies.
   
4
Mason Training programs:  
79 masons were trained by conducting 8 mason training programs in all 8 districts. They obtained on the job training on construction of RWH system.  
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
     
   
5 Tank constructions:
  Beneficiary sites were identified with the help of local organisation and partners in all eight districts of the North and East districts and a total of 93 RWH tanks were built.
   
  The number of Tanks built in Each District:
 
  Jaffna 14
  Kilinochchi 09
  Vavunia 21
  Mullaitivu 02
  Mannar 10
  Trincomalee 13
  Batticaloa 11
  Ampara 13
     
   
 
 
     
Demonstration RWH tank connected to a drip irrigation system at District Agriculture Training Centre, Ellappiar Maruthankulum, Vavuniya   Demonstration RWH tank (VA 04) at Kalimakal Vidyalaya, Unit 06, Pavatkulum, Vavuniya
     
   
6 Operation & Maintenance programs 
  - 33 awareness programs on Operation and Maintenance (O&M) of RWH systems were conducted for direct beneficiaries of the RWH systems. 633 persons participated in these programmes.
  - A Socio economic survey of the beneficiaries was conducted.
   
7 Strengthening of partners 
  - Reusable frames used for construction of ferrocement RWH tanks were distributed to partners in each district.
   
   
8 Resource material/ Publications
  - 3 Volumes of “Varsha” newsletter was printed & distributed.
  - RWH manual titled “Problem-Water: Solution-Rainwater” was translated and published in Tamil.
  - Brochures in all 3 languages were printed and distributed.
  - O&M manual was translated and printed and distributed to beneficiaries.
  - Posters in all 3 languages were printed.
 
     
   
     
 
 
     
     
     
 
     
     
     